Jurong Port Pte Ltd – Singapore

Scope of work:

Design, Supply, Installation, Commissioning of 3 Aggregate Wharf Conveyor at Berth J12, Jurong Port.

Handling material:

Aggregate / Sand

Capacity:

1000tph

Completion date:

Feb 2023

Scope of work:

Design and Build of Sugar Dumping Station and Conveyor to Raw Sugar Warehouse

Handling material:

Raw Sugar

Capacity:

640tph

Completion date:

Dec 2020

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Completion, Testing & Commissioning for Coal Handling System

Handling material:

Coal

Capacity:

1000tph

Completion date:

Feb 2020

Scope of work:

Installation of Stacker And Reclaimer

Handling material:

Coal

Capacity:

1000tph

Completion date:

Dec 2019

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Completion, Testing & Commissioning for Coal Handling System

Handling material:

Coal

Capacity:

1000tph

Completion date:

Jan 2020

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Testing & Commissioning for Slurry Treatment Plant

Handling material:

Abrasive Rock

Capacity:

500tph

Completion date:

Jun 2019

Scope of work:

Design, Engineering, Procurement, Fabrication, Installation & Commissioning of 0.24km, 1.73km & 1.31km Belt Conveyors

Handling material:

Coal

Capacity:

1000tph

Completion date:

Mar 2019

Scope of work:

MSM Sugar Refinery for the Supply and Installation of Refined Sugar Belt Conveyors

Handling material:

Refined Sugar

Capacity:

15 -100tph

Completion date:

Jan 2019

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Completion, Testing & Commissioning for Bucket Elevators, Screw Conveyors & Mingler

Handling material:

Refined Sugar

Capacity:

15-100tph

Completion date:

Jan 2019

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Completion, Testing & Commissioning for Coal Handling System

Handling material:

Coal

Capacity:

1000tph

Completion date:

Oct 2018

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Testing & Commissioning for Raft Conveyor System

Handling material:

Raft

Capacity:

10tph

Completion date:

Oct 2018

Scope of work:

Design, Engineering, Supply, Fabrication, Installation, Completion, Testing & Commissioning for Raft Conveyors for Water Theme Park

Handling material:

Raft

Capacity:

10tph

Completion date:

Mar 2018

Scope of work:

Design & Detail Engineering of 2.7km & 0.7km Pipe Conveyors, Belt Conveyors and Ship loader

Handling material:

Silica Sand

Capacity:

800tph

Completion date:

Dec 2017

Scope of work:

Engineering, Supply and Installation of Belt Conveyors, Bucket Elevators & Plant Equipment

Handling material:

Fertilizer

Capacity:

20tph

Completion date:

Apr 2016